Bedrock
Intelligence
Field ViewAutonomy Nominal
MST · 07 Jul 2026
JR
Site Command Center

I‑10 Mass Excavation — Today

6 autonomous units · 4 work zones · plan v14 · last field verification 08:15

Production
8,240
yd³
91% of daily plan
+4.2%
Schedule Risk
+1.6
days
at current rate
worsening
Autonomous Runtime
74
%
6.2h / 8.4h shift
+11 pts vs 7d
Fleet Ready
5
/ 6
next shift
EX-14 flagged
Interventions
12
concentrated in Zone C
8 route, 3 sensor, 1 obstacle
Human Exposure
-63
%
vs manned baseline
42 hrs offloaded
Site Location
Casa Grande, AZ · I‑10 Corridor
32.879° N · 111.756° W
Site aerial reference
I‑10LAPhoenixTucsonEl PasoSITE 04 · SUNDTI‑10 Mass Excavation · 214 ac
Bedrock deployment · civil earthmoving
Elev 434 mWx 31°C · wind 8 ktSunset 19:34
Site Map
Live operations — 1:2000
On trackAt riskBlocked|Δ 12s
Site aerial referenceZONE A · North Cut3,410 / 3,200 yd³ · 107%ZONE B · Central Fill2,960 / 2,800 yd³ · 106%ZONE C · South Haul Corridor1,870 / 2,600 yd³ · 72% · blockedSTOCKPILE · detected 10:42ZONE D · StagingAwaiting release · plan window 13:00EXEX-11HTHT-05DZDZ-07DZDZ-09LAST KNOWN · 14mEXEX-14HTHT-03
Needs Attention
3 open
auto‑ranked
  • 10:42·Zone C·hazard
    Haul route blocked — stockpile detected on Route C
    Lidar delta > 1.8m across 12m of planned corridor. HT-03 halted, HT-05 rerouted via East loop (+7 min/cycle).
    conf
    94%
    src: EX-14 lidar · HT-03 fwd cam · site plan v14
  • 10:11·Zone C·warn
    EX-14 sensor calibration drift — confidence 72%
    GNSS/IMU residuals rising over last 45 min. Autonomy holding within envelope; 3 disengagements since 09:30.
    conf
    72%
    src: onboard diagnostics · autonomy stack
  • 09:47·Zone B·info
    Zone B pacing above plan — consider reassigning Truck 3
    Central Fill 106% of plan-to-time. HT-05 idle time in Zone A rising; reassignment could recover ~40 min today.
    conf
    81%
    src: cycle counter · utilization model
Metric Trust
Freshness & confidence
nominal
Cubic yards moved
97%conf
Δ 12s · field 08:15
Autonomous runtime
99%conf
Δ 4s · auto
Schedule forecast
78%conf
Δ 1m · supt. 09:30
Production
Cumulative yd³ · plan vs actual
-8.4% to plan
07:0009:0011:0013:0015:30
Autonomy Mix
Shift runtime breakdown
+11 pts vs 7d
  • Autonomous74%
  • Assisted11%
  • Manual8%
  • Idle / Blocked7%
Next Shift Readiness
Fleet check — 15:30 handoff
1 flagged
  • EX-11
    Excavator
    ZA
    98%
  • EX-14
    Excavator
    ZC
    72%
  • DZ-07
    Dozer
    ZB
    95%
  • DZ-09
    Dozer
    ZB
    Telemetry stale · 14 min
    — —
  • HT-03
    Haul Truck
    ZC
    91%
  • HT-05
    Haul Truck
    ZA
    89%